40MW Kabwe Makombe Solar

A strategically positioned 40MW solar asset targeting Zambia’s North-South Backbone. Engineered for Open Access bilateral trade to high-demand mining off-takers.

Project

KABWE ONE SOLAR PLANT

Our flagship project in Kabwe is a strategic early-stage development asset. Positioned directly on Zambia's primary logistics and transmission corridor, this project serves as the blueprint for our Open Access strategy: leveraging deep local grid integration expertise to deliver a structurally sound, high-yield asset to high-demand mining off-takers.

Project Snapshot

Project Name:
KABWE ONE
Target Capacity:
40 MWac / 48 MWp
Location:
Makombe Farms, Kabwe District, Central Province (Adjacent to Great North Road)
Land Status:
50 Hectares (Exclusivity Secured via Option Agreement)
Grid Interconnection:
Proximate to ZESCO 330kV/66kV/33kV Transmission Backbone (Subject to pending Grid Impact Study)
Technology:
Monocrystalline Bifacial PV (Fixed Tilt)
Development Status:
Pre-Development (Executing ZEMA ESIA & Grid Impact Studies)
Legal Status:
Developed by Zubalight Energy Ltd. (EIZ Registered Engineering Firm)

Strategic Energy

Located at Makombe Farms along the Great North Road, this 50-hectare site offers Tier-1 solar irradiation (~2,150 kWh/m²/year) and direct proximity to the ZESCO 330kV/66kV/33kV transmission backbone. Final grid interconnection mechanics remain subject to the pending Grid Impact Study (GIS).

PROJECT HIGHLIGHTS

Pre Development Milestones

Land Asset & Secure Tenure (50 Hectares)

  • Capacity: The site geometry is optimized for a standalone 40 MWac (48 MWp) fixed-tilt array, with zero shading obstructions.

  • Security: This is private leasehold land. This ensures a clean, rapid, and bankable title transfer to the Project SPV strictly upon achieving Financial Close.

Grid Interconnection

  • Technical Reality: The site is bisected by the ZESCO National Transmission Backbone (330kV/66kV/33kV). We are targeting a Direct Line Tap (T-Off/LILO) interconnection to minimize external transmission CAPEX.

  • Validation: Final grid interconnection mechanics, thermal capacity, and voltage stability remain strictly subject to the pending Grid Impact Study (GIS). We do not assume grid viability; we engineer it.

Commercial Strategy: Open Access

  • The Model: This regulatory framework legally permits Zubalight to wheel power across the national grid directly to USD-paying, high-credit consumers (Mining Majors) or trade via the Southern African Power Pool (SAPP) using aggregators like GreenCo.

  • The Urgency: With the national energy crisis severely hampering the mining sector’s goal of 3 Million Tonnes of Copper, Kabwe One offers a highly targeted, private-to-private baseload solution.

The Technical Leadership

  • The Brain Trust: Our executive leadership includes the former Director of Distribution at ZESCO (who managed the national grid) and a former Project Manager at the Industrial Development Corporation (IDC).

  • Execution Risk: We understand the technical realities of the ZESCO grid code and Zambian statutory compliance because our leadership helped engineer and enforce them.

Scalable Energy Platform

TIMING IS EVERYTHING

The National Context

The Investment Opportunity

  • Growing Demand: A structural national power deficit of 600+ MW creates immediate market absorption for new generation.

  • Regulatory Support: A pro-investment environment with clear frameworks for “Open Access” grid utilisation.

  • Strategic Offtake: A flexible commercial model allowing for optimised PPA structures that align with investor and lender requirements.

  • Fiscal Incentives: 0% Import Duty on Solar Equipment and strong government support for renewable energy infrastructure.